The following project was performed by our restoration partner in North Carolina:
First Restoration Services 

 

United States Pentagon
Washington, D.C.

Loss Description: 
September 11, 2001 the crash site at the Pentagon was in flames. Massive amounts of water and chemicals were necessary to douse the fires before any kind of clean up could begin.   

Unique Issues:
Extensive security precautions were in place for the site, which was also viewed as a crime scene. The high quality of the First Restoration crews resulting in getting initial Pentagon security clearances in three days when the “norm” is two weeks. Workers were brought in daily thereafter in a van, which went through several security checkpoints. Heavily armed guards, bomb sniffing dogs and under vehicle inspections was the norm. 

  
Job Elements:
Mitigation: First Restoration Services worked in what is known as Wedge two - a 300,000 square foot area of the building immediately adjoining the damaged portion of the Pentagon. First Restoration’s experience and reputation for performing large scale commercial structural and contents drying while filtering the air of asbestos, lead paint and mold particles was key to their successful completion of this project.

Project Recognition:
First Restoration Services, one of the largest Restoration Partners within the IntegResource network, was selected due to being one of the only resources with this capability in the country.   

Back to Top

The following project was performed by our restoration partner:
Electronic Decontamination Specialists:

Fuji Securities

World Financial Center, NY, NY

 

Loss Description:

On September 11, 2001 Fuji had $20 million worth of computers, including servers, routers and other complex data equipment located on the 26th floor directly adjacent to where the World Trade Towers used to stand.  

 

Unique Issues:

Falling debris and the compression of air from the collapsing towers blew out hundreds of windows in the neighboring high-rise buildings.  This in turn allowed dust and smoke to enter these buildings contaminating everything.

 

One of the main challenges surrounding this job was limited access to receive materials.  Congestion and security severely limited delivery access to the building because of the close proximity to Ground Zero.  Therefore, boxes and packaging materials had to be delivered and off-loaded as far as a mile away and hand carried into the high-rise facility.  When you consider the hundreds of boxes and rolls of protective wrap that had to be hand carried it became quite a logistical juggling act to pull this project together.

 

  
  
  

Job Elements:

Electronics Decontamination Specialists set up temporary workstations that allowed the equipment to flow from one process to the next in an organized and methodical fashion.  The first step in the process was to apply a barcode inventory label to each item with the brand, model, serial and other specific information about that piece.

 

The next step in the process was to component clean the items to remove contaminants.  Disassembly was required to perform this task.  The items then flowed to the diagnostics & testing stations where each and every piece of equipment was tested for proper function and operation.  If they failed, they were sorted for insurance inspection and/or salvage.

 

From there the equipment flowed to the packaging area where items were carefully packaged in anti-static protective wrap and placed into heavy gauge cartons that would offer the required protection during the transport process to the storage facility.  A larger self-adhesive type barcode label was then affixed to the outer facings of the cartons that would record a detailed inventory and status record of the equipment placed in the carton.

 

The boxed equipment was then row stacked in preparation for transfer.  In addition to this work, the entire data room was dismantled and de-wired and server racks prepared for shipment.  Security cameras and other tenant equipment was removed, cleaned, tested and packaged for the move to their new facility.

 

Project Recognition:

Electronic Decontamination Specialists was able to complete the project on time, ensuring client satisfaction and another great referral for IntegResource.

 

Back to Top

The following project was performed by our restoration partner in North Carolina:  
First Restoration Services
Prince George's Metro Center
Hyattsville, Maryland
  

Loss Description:
On November 24, 2000, this nine story, 283,500-square-foot office building suffered damage due to a 2.5" sprinkler water supply line that burst in the seventh floor ceiling, disbursing 500,000 gallons of water throughout the building. This approximately 30-year-old building had been renovated at least twice, contributing to water disbursal due to a number of open pipe chases. Cable runs throughout each floor also created extensive water collection areas.
  
The offices in the building included solid wall offices along with a large number of office cubicles and dividers. In addition to the walls and office dividers experiencing water damage, contents and documents were also soaked.
  
This building was one of three identical buildings in the complex. Some of the issues that made this loss unique were the variety of tenants, which included FEMA (one of three facilities nationwide where financial assistance claims for disaster services are processed), Prince George's Community College, Prince George's County Department of Social Services and several other businesses. One floor was also in the process of being built out when the damage occurred.
  
 
 
  
  
  
Unique Issues:
Prolonged exposure to excessive moisture, possibly encouraging the flourishing of fungal or bacterial spores, was a concern. This necessitated involvement from teams of Industrial Hygienists and other experts by FEMA, First Restoration Services, Prince George's County, the State of Maryland, the building's insurance company and GSA.

 Job Elements:
Phase I Mitigation: Two different emergency services companies were initially brought in and performed some water extraction during the first 24 hours. However, as the job progressed and the extent of the damage was further identified, FRS assumed responsibility for the entire structure.
  
Phase II Reconstruction: FRS worked with another company that performed the reconstruction once the building was dried and stabilized. FRS was able to dry the structure to a point where, in some areas, reconstruction costs were less than mitigation costs. These isolated areas were identified at the end of the drying process for the construction manager.
  
Project Recognition:
First Restoration Services was selected for this project due to it's reputation for responding quickly and our proven ability to handle losses of such complexity and magnitude.

 Back to Top

The following project was performed by our restoration partner headquartered in Utah:
Utah Disaster Kleenup (UDK):
Western Wyoming Community College
Rock Springs, WY
  
Loss Description:
January, 2001 A fire erupted in the mechanical room of Western Wyoming Community College located in Rock Springs, WY. The fire occurred just weeks before the school resumed from Holiday break. Approximately 300,000 square feet of the 500,000 square foot facility was affected by moderate to heavy smoke and the additional 200,000 square feet suffered light smoke damage. The odor throughout the entire facility was severe.
 
 
  
Unique Issues:
UDK designed and constructed airtight barriers that were installed in strategic locations throughout the facility to isolate the 50,000 SF mechanical area of the building where strong odor and complete reconstruction of the roofing & mechanical systems were in process. With the installation of high volume exhaust fans the clean areas of the building were kept under negative pressure, forcing mal-odor and contaminants away from the clean environments.
  
Job Elements:
Phase I Mitigation: Utah Disaster Kleenup was mobilized and on location within 24 hrs. Key supervisory, estimator and secretarial staff were able to control and direct temporary staff transported from Salt Lake City and local personnel from the Rock Springs communities. UDK had to guarantee all cleaning and odor remediation work could be completed within two weeks so that school could resume on schedule with no interruptions or complaints from students or faculty members regarding indoor environmental issues. UDK worked personnel seven days per week 12 hours per day and provided on site meals and refreshment breaks to keep workers nourished and strong.
  
Project Recognition:
The project was completed and ready for full occupancy three days prior to the scheduled opening date. The college staff considered the building to be cleaner than it has been since it was constructed. There was no trace of malodor anywhere in the entire building. School started on time with no interruptions and little awareness that a substantial fire loss had occurred in this 500,000 square foot facility.
Back to top    
         
 4161 Carmichael Ave., # 203 Jacksonville, FL 32207 • tel: (877) 629-6688 • fax: (904) 398-9804